The ECIS rebates are only applicable for active MSS accounts. If you already have an active MSS account, the next step is to determine whether your solar PV system has been installed and commissioned.
1) If your solar PV system has not been installed, please contact our Supply Application department, who is the main liaising point for solar PV system commissioning, at 6916 7200 or install@spgroup.com.sg for assistance.
2) If it has been installed, please submit the Application for Net Export Rebate form which can be downloaded from www.openelectricitymarket.sg.
Upon receiving the Application for Net Export Rebate form, a separate generation account will be created for the net export rebate payment from SP Group to you. We will then liaise with the Meter department to install a generation meter or replace the existing AMI meter with a bi-directional AMI meter, depending on the type of meter currently installed at your premises.