No earthwork is to be carried out within the 7 calendar days' notice after a NCE is submitted. However, we may consider earlier commencement of earthworks on a case-by-case basis. You may wish to submit your request to commence earthworks earlier than stated in your NCE to SP PowerGrid via fax, giving the reasons for doing so. Such requests may only be granted, subject to:
- A valid reason
- Letter of requirements from ESP has been issued and
- Satisfactory compliance with all precautionary measures