SPPA Transmission Cable Tunnel Project
Project Schedule
Construction works for the North-South and East-West tunnels are expected to commence in the first quarter of 2013. The East-West tunnel is expected to be completed in May 2017 while the North-South tunnel, which is longer, is expected to be completed in April 2018.
Key milestones:
- 18 Sep 2012 – Contract Award Signing Ceremony
- January 2013 – Commencement of Construction
- May 2017 – Completion of East-West tunnel
- April 2018 – Completion of North-South tunnel